Tue, Dec27, 2011
Business News Americas reported in early December that the Bolivian government has equipped the armed forces with barges to help export iron ore from Santa Cruz department's El Mutún deposit.
A sector executive told BNamericas “There is a decree under which the armed forces will undertake 30% of transport so they can help export the iron ore via the Paraguay Paraná waterway to the Atlantic ocean.”
The government gave the armed forces two trawlers and 16 barges that can move up to 2,500 tonnes.
However, some infrastructure works still need to be completed, according to the executive, and they need to organize return cargo so they are not just exporting but also importing.
Iron ore exports from El Mutún are currently suspended due to the low level of the Paraguay River and will not resume until next year.
At the beginning of October, state steel company ESM sent the first 10,000 tonnes of iron ore to Paraguayan steelmaker Acepar as part of a USD 6 million sales contract for 140,000 tonnes.
(Sourced from Business News Americas)
Showing posts with label Bolivian iron ore. Show all posts
Showing posts with label Bolivian iron ore. Show all posts
Tuesday, December 27, 2011
Bolivia provides armed forces with barges to transport iron ore
Monday, October 10, 2011
Bolivia may end contract with India’s Jindal Steel
Monday, 10 October 2011
India-based steelmaker Jindal Steel & Power Ltd. faces threats from the Bolivian government to end its contract with the company, according the media reports. The Bolivian Ministry of Energy has suggested that Jindal Steel deceived Bolivia, failing to meet its commitments regarding iron ore mine investment.
As SteelOrbis previously reported, Jindal Steel and the Bolivian government signed a $2.1 billion investment contract in 2007 to mine and smelt 40 billion mt of iron at Mutun on Bolivia's border with Brazil.
Tags: iron ore , raw mat , Bolivia , India , Indian Subcon , South America , Jindal , investments , South Asia
(sourced steelorbis)
India-based steelmaker Jindal Steel & Power Ltd. faces threats from the Bolivian government to end its contract with the company, according the media reports. The Bolivian Ministry of Energy has suggested that Jindal Steel deceived Bolivia, failing to meet its commitments regarding iron ore mine investment.
As SteelOrbis previously reported, Jindal Steel and the Bolivian government signed a $2.1 billion investment contract in 2007 to mine and smelt 40 billion mt of iron at Mutun on Bolivia's border with Brazil.
Tags: iron ore , raw mat , Bolivia , India , Indian Subcon , South America , Jindal , investments , South Asia
(sourced steelorbis)
Friday, January 21, 2011
JSPL to export Bolivian iron ore in March - Report
Friday, 21 Jan 2011
State run daily Cambio reported that India's Jindal Steel and Power is due to start exporting iron ore concentrate from Bolivia's El Mutun in March.
The report, without specifying when the comments were made, quoted Mr Naveen Jindal vice CMD of JSPL as saying that “Beginning iron ore exports toward the end of March will be an important milestone.”
The state run newspaper also reported Jindal as saying that El Mutun should start producing steel by 2014.
Mr Jindal had told Reuters earlier this month that the company plans to invest USD 280 million in el Mutun in 2011 and said it will export up to a million tonnes of iron ore in this first year of operations.
The USD 2.1 billion iron ore and steel project in eastern Bolivia has been plagued by delays amid accusations by Bolivia's leftist government that the company was running behind schedule. A 40 year contract gives Jindal the right to mine about half the El Mutun site, which is believed to contain some of the world's largest reserves of iron ore, though said to be of medium grade quality.
(Sourced from Reuters)