Google Website Translator Gadget

Showing posts with label Vijaynagar plant. Show all posts
Showing posts with label Vijaynagar plant. Show all posts

Friday, July 8, 2011

JSW Steel to halt expansion of Vijayanagar unit


Fri, July 8, 2011

Bangalore : JSW Steel will not go ahead with its proposed expansion plans at its Vijayanagar (Bellary) unit until it receives approval for captive iron ore mine in Karnataka.

It had earlier evinced interest to expand the capacity of the Vijayanagar facility to 16 million tonnes (mt) from 10 mt.

Vinod Nowal, chief executive officer and director of the company, said, “We will not expand the capacity to 16 mt until there is a captive iron ore source available to us.” He was speaking to reporters on the sidelines of a seminar organised by the Bangalore Chambers of Commerce and Industry here.

The Supreme Court yesterday refused to entertain a plea of the company to direct the Karnataka government to lease a captive mine for the plant. The court was not convinced by JSW’s submission that it made an investment of Rs 10,000 crore by setting a steel plant on the assurances of the state government that a captive mine would be allotted to it. It, however, allowed the company to appeal in the Karnataka High Court with its grievances.

“Our legal department is examining the case and we will appeal in the high court,” he said. Despite operating a 10-mt steel plant in Karnataka, the company doesn’t have any captive iron ore source in the state. It is procuring iron ore from Orissa, Chhattisgarh and Jharkhand to feed the plant. Nowal said the supply situation with respect to iron ore was tight and the company had stocks for 10 days only.

It reported a 29.8 per cent growth in net profit at Rs 793.6 crore for the fourth quarter of the last financial year. Net sales rose 32.5 per cent to Rs 7,209.3 crore from Rs 5,441.3 crore in the previous corresponding period.

(By Business Standard)

Saturday, February 19, 2011

JSW Steel raises funds for cold rolling mill at Vijaynagar

Saturday, 19 Feb 2011

ET reported that JSW Steel has tied up funds for its 2.3 million tonnes cold rolled mill at its Vijaynagar plant.

As per report, JSW has raised USD 280 million (INR 1280 crores) via external commercial borrowing. The total project cost is INR 4025 crores.

Rest of the debt will be tied up via ECA or external commercial assistance while buying equipments for the plant and JSW Steel will infuse INR 1300 crores of equity funding via internal accruals.

JSW Steel plans to build 1.9 million tonnes of continuous annealing line and 0.9 million tonnes of galvanizing, galvannealing line.

The company aims to finish the first phase by Q1 FY 14 and phase 2 by Q1FY15.

(Sourced from ET)